AES Indiana is investing in the electric transmission system to help improve reliability, meet increased demand and provide operational flexibility for all customers within and surrounding AES Indiana’s territory. The improvement project involves building approximately 11 miles of new transmission lines, rebuilding two miles of existing transmission lines and a new substation.
Project map
Visit the Northwest Expansion project map to view proposed project.
Building 11 miles of single circuit 138kV transmission line
Rebuilding 2 miles of single circuit 138kV transmission line
Typical structures
The project involves the use of both steel and ductile iron poles, with heights ranging from 80 ft.-105 ft. and an approximate right-of-way easement of 30 ft.-75 ft.
The project involves the use of both steel and ductile iron poles, with heights ranging from 80 ft.-105 ft. and an approximate right-of-way easement of 30 ft.-75 ft.