
RFP milestone dates and deadlines
Milestone dates for the RFP process are presented below. AES Indiana reserves the right to extend or otherwise modify any portion of this schedule at any time or terminate this RFP process at its discretion at any time prior to contract execution without liability to any party. Any such changes will be posted on this page.
Milestone |
Date |
RFP released to public |
February 13, 2023 |
Bidder site visits |
February 23, 2023 |
Respondent clarification submittal deadline |
February 27, 2023, 5:00 PM Central |
Respondent proposal submission date |
March 20, 2023, 11:59 PM Central |
EPC Agreement execution |
April 15, 2023 |
Limited notice to proceed (LNTP) |
April 22, 2023 |
Full notice to proceed (FNTP) |
September 30, 2023 |
Commercial operation date (COD) |
December 1, 2024 |
Substantial completion |
December 31, 2024 |
Additional resources
RFP overviewAll about the 2023 BESS RFP.
RFP documentsLearn how to submit an RFP proposal.
RFP Q&ARead RFP questions and answers.