RFP milestone dates and deadlines
Milestone dates for the RFP process are presented below. AES Indiana reserves the right to extend or otherwise modify any portion of this schedule at any time or terminate this RFP process at its discretion at any time prior to contract execution without liability to any party. Any such changes will be posted on this page.
Milestone |
Anticipated date |
RFP released to public |
April 7, 2023 |
RFP webinar |
May 3, 2023 |
Respondent clarification submittal deadline |
5:00 PM Central, May 16, 2023 |
Respondent proposal submission date |
June 30, 2023 |
Conclusion of Phase I evaluation selection of shortlisted proposals |
Q3 2023 |
Conclusion of Phase II evaluation selection of proposals for contract negotiation |
Q4 2023 |
Due diligence and negotiation period |
Q4 2023-Q1 2024 |
Definitive agreement(s) executed with selected respondent(s) |
Q2 2024 |