RFP milestone dates and deadlines
Milestone dates for the RFP process are presented below. AES Indiana reserves the right to extend or otherwise modify any portion of this schedule at any time or terminate this RFP process at its discretion at any time prior to contract execution without liability to any party. Any such changes will be posted on this page.
Milestone |
Anticipated date |
RFP released to public |
April 14, 2022 |
RFP webinar |
April 21, 2022 |
Respondent clarification submittal deadline |
5:00 PM Central, May 3, 2022 |
Replacement of existing generating facility respondent proposal submission date |
May 16, 2022 |
Respondent proposal submission date |
May 19, 2022 |
Conclusion of Phase I evaluation selection of shortlisted proposals |
Third Quarter 2022 |
Conclusion of Phase II evaluation selection of proposals for contract negotiation |
First Quarter 2023 |
Due diligence and negotiation period |
First and Second Quarter 2023 |
Definitive agreement(s) executed with selected respondent(s) |
Second Quarter 2023 |
Additional resources
Project scheduleRFP milestone dates and deadlines.
RFP documentsLearn how to submit an RFP proposal.
RFP Q&ARead RFP questions and answers.